Kraton Chemical
Here is the crane hoisting up some materials to the roof. 03/21/2017 After the banners are in place, the roof got loaded with the need supplies. 03/21/2017
Here is another view of our supplies after they were loaded and covered. 03/21/2017
Kraton Chemical
Here is a view of one of the skylight sections before we started Roofing. 03/22/2017 In the photo you can see the insulation fill in the flutes of the existing metal deck with the 1.5 insulation of top screwed down with rhino bond plates. 03/22/2017
After the insulation and metal deck is screwd down, fibertite is rolled out and rhino bonded to the plates. 03/22/2017 Now that all the fibertite is down and welded we can now wrap the boxes and run the termination bar. 03/22/2017
Angle change plates are ran and screwed down into the deck below. 03/22/2017 The curbs are then wrapped with with fibertite material and sealed. 03/22/2017
Here is a view of one of the sections after the curb was wrapped and the termination bar was installed on the side of the Fibertite roof. 03/22/2017 A bead of water cutoff was installed behind the material and termination bar to prevent water from coming in behind the material. 03/22/2017
Kraton Chemical
Here is one of the skylights while we were filling the flutes with insulation. 03/23/2017 Here's the one section afte the insulation was installed and screws down. 03/23/2017
New fibertite material is then rolled out and cut into place. The material is then rhino bonded to the plates below. 03/23/2017 A bead of water cutoff is laid into place along the outer edge of the metal rib. 03/23/2017
Termination bar is now screwd into place along the metal rib. 03/23/2017 Here's one of the sections we did today after we were done for the day. 03/23/2017
Kraton Chemical
Here's one of the section before we laid in the insulation fill. 03/24/2017 The fill has now been installed and is ready for the top layer of 1.5 insulation. 03/24/2017
After the 1.5 is installed, insulation plates are acres down to the insulation surface. 03/24/2017 Fibertite is now rolled out and rhino bonded to the welder friendly insulation plates underneath. 03/24/2017
Here is one of the sections after we were done for the day. 03/24/2017 Here is a view of the other section. 03/24/2017
Kraton Chemical
Here is the section of skylight that we roofed today. 03/29/2017 ISO fill is installed 5 flutes wide around the skylights for stability when we add the top layer. 03/29/2017
The top layer of 1.5 insulation is cut into place and fastened down with plates and screws. 03/29/2017 Fibertite material is now rolled out and rhino bonded into place. 03/29/2017
Now that both sheets have been installed they are welded together for a warertite seal. 03/29/2017 Angle change plates are screwd in around the skylight to hold the field sheet into place. 03/29/2017
Fibertite pieces are then tacked into place in preparation to wrap the skylight. 03/29/2017 The pieces are then welded together for a watertite seal around the skylight. 03/29/2017
Kraton Chemical
Here is the bottom of one of the roofs after it was cut and flashed in. 03/30/2017 This the bottom of another section after then men finished flashing it in. 03/30/2017
Here is the termination bar after all the screws were installed. 03/30/2017 Here is where the peak was terminated with termination bar. 03/30/2017
Kraton Chemical
Here's a view of two of the skylights we roofed today. 04/03/2017 New insulation fill is being installed into the metal flutes. 04/03/2017
Now that the fill and 1.5" insulation is installed, screws and plates are then used to secure it to the deck. 04/03/2017 Fibertite membrane is then rolled out and cut into place. The plates are then heat welded to the FiberTite membrane. 04/03/2017
After the FiberTite membrane is installed and welded a bead of cut off in placed on the metal rib so termination bar can be installed. 04/03/2017 Here is a view of one of the sections after we were done for the evening. 04/03/2017
Kraton Chemical
One of the skylight bottoms after it was cut and flashed in. 04/04/2017 Water cutoff was placed under the material and termination bar was screwed in. 04/04/2017
One of the skylights after it was wrapped and flashed in with the FiberTite membrane. 04/04/2017 Here you can see the counter flashing has been installed and the termination bar has been caulked. 04/04/2017
We also probed the roof. Any bad spots are marked with a red marker and then patched with FiberTite. 04/04/2017
Kraton Chemical
We had to flash in two of the peaks on the new FiberTite roof. 04/05/2017 We installed the rest of the termination bar at the bottoms of the FiberTite roofs. 04/05/2017
A view of the roof after we were done. 04/05/2017 An overview of the FiberTite roof after we were done. 04/05/2017
Here is a view of the other side of the roof. 04/05/2017